Project Handbook in PM²: the project’s operational reference

Twenty-sixth article in the “Learning PM² Through a Project” series

A project can have a clear Charter and still work in a confused way: roles are not updated, plans are scattered, logs are hard to find, each person follows different rules and decisions lack a reference point.

The PM² Project Handbook is the operational container that brings together the information needed to manage the project consistently. It is not a document written to be archived: it must be accessible, maintained and tailored to actual project complexity.

Charter, Handbook and Work Plan: three different levels

ArtefactQuestion it answers
Project CharterWhat is the project, why does it exist, who governs it and what are its initial limits?
Project HandbookHow will the project be organised and managed day to day?
Project Work PlanWhich work will be done, with which estimates, dependencies and dates?

The Handbook does not replace the other two. It connects them: it starts from the Charter mandate, incorporates or refers to plans, and makes the Work Plan usable through roles, processes, logs and operating rules.

What the Project Handbook contains

PM² structures it as a collection of elements that the PM tailors to the project. Not everything must always be present or have the same detail level.

SectionTypical content
Roles and responsibilitiesProject organisation, governance, RAM/RASCI and delegations.
Project Management PlansPlans for requirements, changes, risks, issues, quality and communication.
Project-Specific PlansAcceptance, transition, business implementation and outsourcing plans, where relevant.
Domain-Specific ArtefactsTechnical, security, data-protection, UX, procurement or other applicable artefacts.
Other referencesProject Work Plan, Stakeholder Matrix, logs, repository, tools, conventions and decisions.

The Handbook may be a structured document with annexes, a collaborative space with linked pages or a set of versioned artefacts. What matters is an authoritative source, an understandable structure and current references.

The tailoring principle

PM² is intentionally adaptable. Tailoring does not mean removing everything that looks like documentation; it means retaining only what adds value to project control, without losing essential governance and traceability.

SituationReasonable tailoring
Small internal project, stable teamLightweight Handbook, with short sections and essential logs in one space.
Project with many stakeholders and an external supplierMore detailed plans and responsibilities, formalised communication and acceptance rules.
High-risk or regulated projectGreater evidence for quality, security, decisions, audit trail and controls.

It is not tailoring to say: “we do not have time for the Risk Log”. If risk exists, the project needs a proportionate way to manage it. Tailoring chooses form and depth; it does not deny the need.

A useful Handbook is action-oriented

Every section should help someone decide or work better. A simple check is:

ContentUsefulness check
RolesDoes a person know who decides, who performs and who to escalate to?
Risk planIs it clear where to record a risk, who owns it and how to monitor it?
Change planIs it clear how to propose, assess and approve a change?
CommunicationDoes every stakeholder know which information they receive and where to find the official source?
Quality / acceptanceAre criteria, evidence and responsibilities known before delivery?

If the answer is no, adding pages does not solve it: content must become more operational or take a different form.

Governance and responsibilities in the Handbook

The Handbook is the natural place to make RAM/RASCI usable. An organisation chart is not enough: material activities should make clear who is Responsible, Accountable, Support, Consulted and Informed.

ActivityExample Handbook clarification
Approve a material changeWho prepares the analysis, who decides, who is consulted and informed.
Accept a deliverableCriteria, verifier, acceptor and exception handling.
Manage a critical issueOwner, escalation threshold, channel and competent authority.
Prepare go-liveResponsibilities for technical transition, training, support and readiness decision.

This prevents both “everyone is responsible” and “nobody has authority”.

The Annotatio case: a lightweight but complete Handbook

For Smart Bookings, the Handbook does not need to become a hundred-page manual. It can have a practical structure:

SectionContent
OverviewLink to Charter, objective, initial scope, main milestones and official repository.
RolesPO, SP, BM, PM, technical team, pilot managers and RAM for key decisions.
Work PlanLink to the plan with activities, dependencies, owners and dates.
Essential plansLightweight rules for requirements, change, risk, issue, quality and communication.
Acceptance and transitionWaiting-list criteria, tests, go-live checklist, support and notification fallback.
LogsLinks to Risk, Issue, Change and Decision Logs with owner and status.
Technical documentationAPI, push configuration, roles, operating instructions and runbook.

The purpose is not to duplicate information. It is to let a person joining the project quickly understand how work is done, which decisions matter and where the reliable source is.

Versioning and maintenance

A static Handbook quickly becomes dangerous because it gives a false sense of control. The PM should define at least:

  • where the official version resides;
  • who may modify main sections;
  • when changes need review or approval;
  • how updated plans and logs are linked;
  • which version was approved at RfE and which subsequent updates are material.

Not every update needs a committee. Updating a contact or operating date may be routine; changing roles, tolerances or the acceptance process may need a controlled decision.

Do not confuse these

StatementCorrection
“The Handbook is an additional document alongside plans.”It is the container or access point connecting plans, roles, logs and rules.
“Tailoring means reducing documentation to the minimum.”It means calibrating artefacts to value and risk while retaining control and traceability.
“If we have Jira or Teams, we do not need a Handbook.”Tools do not replace structure, rules and an authoritative source.
“The Handbook is completed in Planning and never changes.”Keep it alive as roles, plans, governance or operating conditions change.

Three questions to anchor it

  1. Where would a new member find official rules for managing risks, changes and issues?
  2. Which content deserves a dedicated section because its risk or impact is high?
  3. Which artefact can be simplified without losing an essential decision, responsibility or evidence?

Flashcards

Q: What is the Project Handbook for?
A: To collect and connect roles, plans, logs, artefacts and operating rules needed to manage the project consistently.

Q: What is the difference between Handbook and Work Plan?
A: The Handbook explains how the project is organised and managed; the Work Plan details work, estimates, schedule and dependencies.

Q: What does tailoring mean in PM²?
A: Adapting artefact form and depth to project complexity and risk without eliminating needed control.

Exam-style question

A PM decides not to prepare a Project Handbook because all activities are tracked in a ticketing tool. After a few weeks, the team does not know which acceptance-criteria version is valid, who approves changes or where decisions are recorded.

What is the correct assessment?

Answer: the ticketing tool may contain information, but does not replace a coherent operational reference. The Project Handbook should make structure, roles, plans, official sources and links to logs and artefacts explicit, in a form proportionate to the project.

Source

The Project Handbook, Project Management Plans, Project-Specific Plans and tailoring are covered in the European Commission’s PM² Methodology Guide 3.1.

Next: Project Work Plan, moving from mandate and rules to actual, estimated and sequenced work.